Borough of Oakland Announces 2020 Road Program Schedule
Posted on: September 24, 2020 - 2:15pm
The Borough of Oakland has announced the 2020 Road Program Schedule. Construction includes milling and paving. (Revised - October 2, 2020)
2020 Road Program Schedule: | ||||
---|---|---|---|---|
Order: | Street Name: | Limits: | Milling: | Paving: |
1 | Overlook Ridge | House #43 to End | October 1 | October 7 |
2 | Hidden Gorge | Overlook Ridge to Top Gate | October 2 | October 8 |
3 | Raeben Avenue | Full Length | October 2 | October 8 |
4 | Arrowhead Road | Full Length | October 2 & 5 | October 8 |
5 | Yuma Court | Full Length | October 5 | October 9 |
6 | Truman Boulevard | Roosevelt Boulevard to End | October 5 & 6 | October 9 |
7 | Roosevelt Boulevard | Truman Boulevard to First Street | October 7 | October 14 |
8 | Dacotah Avenue | Full Length | October 7 & 8 | October 15 |
9 | Powdermill Lane | Full Length | October 8 | October 15 |
10 | McCoy Road | House #738 to #748 | October 9 | October 16 |
11 | McNomee Street | Page Drive to Hickory Drive | October 9 & 12 | October 16 |
12 | Demarest Avenue | Walnut Street to End | October 12 | October 19 |
There will be some inconveniences regarding access to and from the residences. Every effort will be made to assure that the inconveniences are minimal. All work will be completed as quickly as possible.
We apologize for any inconvenience you may experience due to the construction activities and appreciate your cooperation.