Borough of Oakland Announces Schedule for 2023 Road Resurfacing Program
Oakland, N.J. - August 18, 2023 - On or about August 22, 2023, construction will commence on the Borough of Oakland's 2023 Road Resurfacing Program. The work includes the milling and paving of the following roadways. Roads are listed in the anticipated order that they will be completed and the order is subject to revisions:
Street Name: | Limits: | Milling Date: | Paving Date: |
---|---|---|---|
Dogwood Drive | Page Drive to Ramapo Valley Road | August 22/23, 2023 | August 28, 2023 |
Hickory Drive | Dogwood Drive to McNomee Street | August 23, 2023 | August 28, 2023 |
Ryerson Street | Hickory Street to Spear Street | August 24, 2023 | August 28, 2023 |
Fox Court | Entire Length | August 25, 2023 | August 29, 2023 |
Nielson Avenue | Grove Street to End | August 25, 2023 | August 29, 2023 |
Speer Street Water Tank Driveway | Entire Length | August 25, 2023 | August 29, 2023 |
Hopper Street | Entire Length | August 25/28, 2023 | August 29, 2023 |
Walton Avenue | Academy Circle to Watnut Street | August 28, 2023 | August 30, 2023 |
Iron Horse Road | Entire Length | August 28, 2023 | August 30, 2023 |
Ramapo Avenue | Entire Length | August 28, 2023 | August 30, 2023 |
Fordham Road | Entire Length | August 28, 2023 | September 1, 2023 |
Chapel Hill Road | Entire Length | August 28, 2023 | September 1, 2023 |
Mountain Lakes Road | Entire Length | August 28, 2023 | September 1, 2023 |
Knollwoods | Entire Length | August 29, 2023 | August 31, 2023 |
Falling Waters | Entire Length | August 29, 2023 | August 31, 2023 |
Hidden Gorge Lower | Overlook Ridge to Lower Gate | August 29, 2023 | August 31, 2023 |
Camp Todd Water Tank Driveway | Entire Length | August 29, 2023 | August 31, 2023 |
Overlook Ridge Water Tank Driveway | Entire Length | August 29, 2023 | August 31, 2023 |
No parking and detour signage will be posted along the roadway at least 24 hours prior to the start of milling and paving. Construction will take place from 7:00 a.m. to 5:00 p.m. Please move your vehicle(s) off of the street by 7:00 a.m. on the dates indicated by the signage. Access to the roadway will be limited until approximately 5:00 p.m. on the days of construction. Every effort will be made to make sure inconveinences are minimal, and that the work is completed as quickly as possible.
For any questions or specific concerns, please contact Boswell Engineering at (201) 334-3045.