PSE&G Announces Milling and Paving Schedule for Borough Roadways

Road Work 2023

June 2, 2023 - Oakland, N.J. - Please be advised that as part of efforts to replace aging natural gas infrastructure in the Borough of Oakland, PSE&G is scheduled to start paving roadways that were trenched to access pipelines. The process will start with milling on Tuesday June 6, 2023, and run through Friday June 9, 2023. Paving is expected to begin on Friday June 9, 2023, and run through Tuesday June 13, 2023.  The list of roadways are as follows:

Street NameBetweenBetweenMilling DatePaving Date
Spear StreetHopper StreetRyerson StreetJune 6, 2023June 9, 2023
Hannah RoadPage DriveEndJune 6, 2023June 9, 2023
Hickory DriveDogwood DrivePage DriveJune 6/7, 2023June 9, 2023
Mandigo AvenueDogwood DriveEnd of TrenchJune 7, 2023June 9, 2023
Spruce StreetRamapo Valley RoadFir CourtJune 7, 2023June 12, 2023
Minnehaha BoulevardSeneca AvenueRamapo Valley RoadJune 8, 2023June 12, 2023
Wenonah AvenueMinnehaha BoulevardPawnee AvenueJune 8/9, 2023June 12/13, 2023
Oneida AvenueWenonah AvenueParts of Iroquois AvenueJune 9, 2023June 13, 2023

Please be advised that this schedule is weather dependent and subject to change.  Should the schedule change in any way,  the Borough will provide an update accordingly.  Traffic will be limited to residents in the immediate area who need to access their homes. Residents are encouraged to follow the posted detours.